Plan pickup around the real staging space after bottling. Count usable pallet positions without blocking cellar access and dispatch routes. Check the carrier time and assign a person to confirm which pallets have been released.
Test the overlap between bottling and pickup
| Timing | No morning pickup | Pickup of eight released pallets first |
|---|---|---|
| Opening stock | 10 pallets | 10 − 8 = 2 pallets |
| Expected new pallets | +18 | +18 |
| Peak occupied positions before later pickup | 28, four beyond the approved space | 20, four available |
| Decision | Reduce or stagger production | Proceed subject to confirmed carrier and release |
Use the plan to agree how many pallets leave before the next batch. Record any hold space separately. Confirm actual pickup vehicle, access and receiving order with the people responsible.
Use the French site and access guide to coordinate warehouse handover with cellar routes.